CMA Intermediate · Cost Accounting · Standard Costing and Variance Analysis
Standard for one unit of a product at Surat Textiles: 5 hours at ₹40 per hour. In a month, 800 units were produced, with 4,200 hours worked and paid at ₹40 per hour. What is the labour efficiency variance?
The labour efficiency variance is ₹8,000 Adverse. Output of 800 units should take 4,000 standard hours, but 4,200 hours were used. The 200 excess hours valued at the standard rate of ₹40 give the adverse variance.
- A₹8,000 Favourable
- B₹8,000 AdverseCorrect
- C₹6,000 Adverse
- D₹16,000 Adverse
Explanation
Standard hours for actual output = 800 x 5 = 4,000. Efficiency variance = (Standard hours - Actual hours worked) x Standard rate = (4,000 - 4,200) x 40 = ₹8,000 Adverse. Using the 4,200 hours only would ignore the output-based standard.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing and Variance Analysis shows your real accuracy, how long you take and where you lose marks.
More Standard Costing and Variance Analysis questions
- Sharma Components budgeted to sell 2,000 units at Rs 50 per unit. It actually sold 2,200 units at Rs 48 per unit. What is the sales price va…
- Budgeted fixed overhead of Rao Components for a month is ₹4,80,000 and budgeted output is 12,000 units, requiring 24,000 standard machine ho…
- In standard costing, a standard that is set on the assumption of efficient operations with allowance for normal wastage, normal machine brea…
- Standard labour rate for a job is ₹60 per hour. Actual wages paid to workers at Pune Fabricators were ₹1,26,000 for 2,000 hours worked. What…
- A firm uses a standard of 4 kg of material per unit at ₹30 per kg. For 5,000 units of actual output, 21,000 kg were purchased at ₹31 and 20,…
- At Nashik Components, 4,000 hours were paid for, but 3,600 hours were actually worked, the rest being idle due to a power failure. Standard …