CA Intermediate · Cost and Management Accounting · Standard Costing

Standard material for 1 unit of a product of Sharma Foods Ltd is 4 kg at Rs 50 per kg. In a month, 1,000 units were produced using 4,200 kg of material purchased and consumed at Rs 48 per kg. What is the material cost variance?

Material cost variance is standard cost for actual output minus actual cost. Standard is 1,000 x 4 x 50 = Rs 2,00,000 and actual is 4,200 x 48 = Rs 2,01,600, so the variance is Rs 1,600 adverse.

  1. ARs 5,000 Adverse
  2. BRs 8,400 Favourable
  3. CRs 1,600 AdverseCorrect
  4. DRs 3,400 Favourable

Explanation

Standard cost for actual output = 1,000 x 4 x 50 = Rs 2,00,000. Actual cost = 4,200 x 48 = Rs 2,01,600. MCV = 2,00,000 - 2,01,600 = Rs 1,600 Adverse. Check: price variance = 4,200 x 2 = 8,400 F; usage variance = 200 x 50 = 10,000 A; net 1,600 A.

Did you get it right without looking?

One question tells you little. A timed set on Standard Costing shows your real accuracy, how long you take and where you lose marks.

More Standard Costing questions