ACCA Applied Knowledge · Management Accounting · Reconciliation of budgeted and actual profit
Standard variable overhead is $4 per labour hour, with 2 hours allowed per unit. In a period, 1,500 units were produced using 3,100 hours (all hours worked were paid) and actual variable overhead cost was $12,800. What is the variable overhead efficiency variance?
The variable overhead efficiency variance is $400 adverse. Producing 1,500 units should take 3,000 hours at 2 hours each, but 3,100 hours were used. The 100 excess hours multiplied by the $4 standard variable overhead rate give $400 adverse.
- A$400 adverseCorrect
- B$400 favourable
- C$1,000 adverse
- D$600 adverse
Explanation
Standard hours for actual output = 1,500 x 2 = 3,000. Actual hours were 3,100, so 100 hours excess x $4 = $400 adverse. The expenditure variance is separate: 3,100 x $4 = $12,400 versus actual $12,800 gives $400 adverse as well, so the total is $800 adverse; $1,000 and $600 do not follow from the data.
Did you get it right without looking?
One question tells you little. A timed set on Reconciliation of budgeted and actual profit shows your real accuracy, how long you take and where you lose marks.
More Reconciliation of budgeted and actual profit questions
- A company uses standard absorption costing with fixed overheads absorbed at $6 per labour hour. Budgeted output was 2,000 units at a standar…
- Trent Co uses standard marginal costing. In an operating statement reconciling budgeted contribution to actual profit, which item must be de…
- Borel Co uses marginal costing. Budgeted sales were 5,000 units with a standard selling price of $20 and a standard variable cost of $12 per…
- Wexford Ltd's standard is 2.5 kg of material per unit at $8 per kg. Actual production was 2,000 units, using 5,200 kg at a total cost of $39…
- Norvik Co's standard is 4 labour hours per unit at $15 per hour. In May it produced 2,000 units using 8,300 hours. What is the labour effici…
- Harlow Ltd's standard labour rate is $12 per hour. In June, 5,000 hours were paid at a total cost of $62,500, and all hours paid were worked…