Skip to content

CMA Intermediate · Management Accounting · Standard Costing and Variance Analysis (Management Accounting)

Standard wage cost for a job is Rs 60,000 (3,000 hours at Rs 20). Actual wages were Rs 66,000 for 3,300 hours paid, of which 100 hours were idle. What is the idle time variance?

The idle time variance is Rs 2,000 Adverse, computed as 100 idle hours multiplied by the standard rate of Rs 20 per hour. Idle time is paid for but unproductive, so it is always an adverse variance.

  1. ARs 2,000 AdverseCorrect
  2. BRs 2,000 Favourable
  3. CRs 6,000 Adverse
  4. DRs 200 Adverse

Explanation

Idle time variance = idle hours x standard rate = 100 x 20 = Rs 2,000 Adverse. Idle hours are always adverse. Rs 6,000 is the total cost variance, not idle time.

Did you get it right without looking?

One question tells you little. A timed set on Standard Costing and Variance Analysis (Management Accounting) shows your real accuracy, how long you take and where you lose marks.

More Standard Costing and Variance Analysis (Management Accounting) questions