CMA Final · Strategic Cost Management · Learning Curve
Sundaram Auto Components expects an 80% cumulative average time curve with a first-unit time of 100 hours. The standard time for units 9 to 16 was set using the learning curve. Actual time taken for units 9 to 16 was 260 hours at a standard rate of Rs 40 per hour. What is the labour efficiency variance for these units?
The variance is Rs 569.60 adverse. Standard time for units 9 to 16 is 655.36 hours for 16 units less 409.6 hours for 8 units, which is 245.76 hours. Actual hours of 260 exceed this by 14.24 hours, and at Rs 40 per hour this costs Rs 569.60.
- ARs 569.60 AdverseCorrect
- BRs 569.60 Favourable
- CRs 2,707.20 Favourable
- DRs 21,600 Favourable
Explanation
Total for 8 units = 8 x 51.2 = 409.6 hours. Total for 16 units = 16 x 40.96 = 655.36 hours. Standard for units 9-16 = 245.76 hours. Variance = (245.76 - 260) x 40 = Rs 569.60 Adverse. Using 8 x 40.96 = 327.68 hours as the standard gives the Rs 2,707.20 distractor, which is wrong. Using 100 hours per unit gives Rs 21,600.
Did you get it right without looking?
One question tells you little. A timed set on Learning Curve shows your real accuracy, how long you take and where you lose marks.
More Learning Curve questions
- Standard time for the first 4 units of a product was set using an 80% learning curve (cumulative average basis) with a first-unit time of 10…
- Mehta Tools uses a 90% cumulative average-time learning curve for a new product. The first unit takes 200 hours. What are the total labour h…
- Ishaan Tools Ltd. applies an 80% incremental unit-time (Crawford) learning curve; the first unit takes 100 hours. Learning is expected to st…
- A firm records that the first unit of a job took 100 hours and the first 4 units together took 324 hours. Assuming a cumulative average lear…
- Kaveri Engineering observes that the first unit of a machine took 200 hours, and the first 4 units together took 648 hours. Assuming the cum…
- Meera Engineering uses an 80% cumulative average learning curve. The first unit needs 50 hours and labour costs Rs 120 per hour. What is the…