Sunil agrees to deliver 50 machine parts to Deepak at Deepak's factory on 10 June. Sunil arrives at the factory at 11 pm on 10 June, when it is closed and no one is present, and leaves the parts at the gate. Next day Deepak refuses to treat this as delivery. Which view is correct under Section 38?
The offer is invalid because it was not made at a proper time and under circumstances giving Deepak a reasonable opportunity to see that Sunil was able and willing to perform fully there and then. Merely leaving parts at a closed factory on the due date does not satisfy Section 38.
- AThe offer is valid, because it was made on the due date
- BThe offer is invalid, because it was not made at a proper time and in circumstances allowing a reasonable opportunity to ascertain ability and willingness to performCorrect
- CThe offer is invalid, only because the number of parts was not stated in writing
- DThe offer is valid, because Deepak refused it later
Explanation
Section 38(2) requires the offer to be made at a proper time and place and in circumstances where the promisee can reasonably ascertain that the promisor is able and willing there and then to perform fully. A late-night drop at a closed factory gives no such opportunity. Being on the due date alone is not enough, and Deepak's later refusal does not cure the defect.
Did you get it right without looking?
One question tells you little. A timed set on Performance of Contracts shows your real accuracy, how long you take and where you lose marks.
More Performance of Contracts questions
- Meera Devi, a painter, promises to paint a portrait for Anil by a fixed date at an agreed price. She dies before that date. According to the…
- Which statement correctly distinguishes Section 67 from Section 38 of the Indian Contract Act, 1872?
- Sunil Traders contracts to supply 200 bags of rice to Kapoor Stores at its godown. Kapoor Stores keeps the godown locked all day and no one …
- Under a contract, Anil promises to supply machine parts to Bharat Engineering by 15 April, and time is of the essence. Anil delivers on 20 A…
- Under the Indian Contract Act, 1872, if a promisee neglects or refuses to afford the promisor reasonable facilities for performance, what is…
- Ramesh Traders promises to deliver 100 bags of rice to Sunita Stores on 1 March against payment of Rs. 50,000. Ramesh, the sole proprietor, …