ACCA Applied Knowledge · Management Accounting · Asset budgeting and investment appraisal
Tarn Co is evaluating a project with an outlay of $100,000 now and a single inflow of $133,100 at the end of year 3. At a 5% cost of capital, the NPV is positive. Using a rate of 10% the NPV is exactly zero. At a cost of capital of 12%, which statement is correct (discount factor at 12% for year 3 is 0.712)?
At 12% the NPV is about negative $5,230, so the project should be rejected. The $133,100 inflow discounted at 0.712 is worth about $94,770, below the $100,000 outlay. This is consistent with the IRR of 10% being lower than the 12% cost of capital.
- ANPV is negative at about $(5,230) and the project should be rejectedCorrect
- BNPV is positive at about $5,230 and the project should be accepted
- CNPV is zero because the IRR is 10%
- DNPV is negative at about $(33,100) and the project should be rejected
Explanation
PV of inflow at 12% = 133,100 x 0.712 = $94,767 (rounded). NPV = 94,767 - 100,000 = $(5,233), approximately $(5,230). The IRR of 10% is below 12%, so the project is rejected. Option $(33,100) ignores discounting.
Did you get it right without looking?
One question tells you little. A timed set on Asset budgeting and investment appraisal shows your real accuracy, how long you take and where you lose marks.
More Asset budgeting and investment appraisal questions
- A company pays $40,000 to install and commission a new machine and a further $6,000 to repaint its existing factory walls. Which statement c…
- Dene Co invests $20,000 today in a deposit paying 6% compound interest per year, with interest added at the end of each year. What will the …
- Marlow Ltd expects to receive $50,000 in 3 years' time. The company's cost of capital is 10% per year. What is the present value of this rec…
- A company is considering a machine costing 200,000 with no residual value. It is expected to generate an average annual accounting profit (a…
- Brook Co plans to buy equipment costing $500,000 with an expected residual value of $100,000 after 4 years. Total cash inflows over the 4 ye…
- A project costs $50,000 now and returns $30,000 at the end of year 1 and $30,000 at the end of year 2. The cost of capital is 10%. Discount …