The board of Nilgiri Power Ltd. defines the maximum amount of loss it is willing to bear in pursuit of its objectives and tells management not to take projects exceeding that level. Which term best describes the level the board has set?

The level set by the board is the risk appetite. It expresses how much and what type of risk the company is willing to accept in pursuing its objectives, and it guides management in deciding which projects fall within acceptable limits.

  1. ARisk appetiteCorrect
  2. BRisk register
  3. CRisk heat map
  4. DResidual risk

Explanation

Risk appetite is the amount and type of risk an organisation is willing to pursue or retain to achieve its objectives. A register is a record of risks, a heat map is a visual rating, and residual risk is exposure after controls. Only appetite is a limit set by the board.

Did you get it right without looking?

One question tells you little. A timed set on Risk Management shows your real accuracy, how long you take and where you lose marks.

More Risk Management questions