CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM
The critical path of a PERT network has an expected duration of 50 days and a variance of 16 days². Assuming the normal distribution applies, and that the area under the standard normal curve up to Z = 1 is 0.8413, what is the probability that the project will be completed within 54 days?
The probability is 0.8413. The standard deviation of the critical path is 4 days, so Z = (54 − 50)/4 = 1, and the cumulative normal area at Z = 1 is 0.8413. The figure 0.1587 would be the chance of exceeding 54 days.
- A0.8413Correct
- B0.1587
- C0.6915
- D0.9772
Explanation
The standard deviation is √16 = 4 days. Z = (54 − 50)/4 = 1, so the probability is 0.8413. The 0.1587 option is the probability of exceeding 54 days (1 − 0.8413). The 0.6915 option comes from wrongly dividing by the variance, which gives Z = 0.25 rather than using the standard deviation.
Did you get it right without looking?
One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.
More Network Analysis - PERT, CPM questions
- In a PERT network the critical path has an expected duration of 50 days. The variances of its four activities are 4, 9, 4 and 8 days squared…
- The critical path of a PERT network of Gujarat Pumps Ltd has three activities with these (optimistic, most likely, pessimistic) times in day…
- A critical activity at Sundaram Constructions has a normal duration of 10 days at a cost of ₹50,000 and a crash duration of 7 days at a cost…
- In a project network, activity P has earliest start 6, duration 5, and its successor Q has latest start 14. P has no other successor. What i…
- A PERT network has two paths: A-C and B-D. Three-point estimates (optimistic, most likely, pessimistic, in days) are: A (2, 5, 8), C (4, 7, …
- A network has these activities with durations in days and predecessors: A (3, none), B (4, A), C (6, A), D (5, B), E (2, C), F (3, D and E).…