Skip to content

CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM

In a PERT network the critical path has an expected duration of 50 days. The variances of its four activities are 4, 9, 4 and 8 days squared. Assuming a normal distribution, what is the probability of completing the project within 55 days? (Normal table: Z = 0.5 gives 0.6915; Z = 1.0 gives 0.8413; Z = 2.0 gives 0.9772.)

The probability is 0.8413. The critical path variance is 25, so the standard deviation is 5 days. The Z value is (55 − 50)/5, which equals 1.0, and the normal table gives 0.8413. The value 0.1587 is the chance of overrunning 55 days.

  1. A0.6915
  2. B0.9772
  3. C0.1587
  4. D0.8413Correct

Explanation

Project variance = 4 + 9 + 4 + 8 = 25, so the standard deviation is 5 days. Z = (55 − 50) / 5 = 1.0, giving a probability of 0.8413. Using 0.6915 would mean a standard deviation of 10, which is wrong. The value 0.1587 is the probability of exceeding 55 days, not of finishing within it.

Did you get it right without looking?

One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.

More Network Analysis - PERT, CPM questions