The reinvestment rate assumption that underlies the NPV and IRR methods is best described as:
NPV assumes interim cash flows are reinvested at the cost of capital, while IRR assumes reinvestment at the project's own IRR. The IRR assumption can be unrealistic for high-IRR projects, which helps explain why the two rankings can conflict and why NPV is preferred.
- ANPV assumes reinvestment at the IRR; IRR assumes reinvestment at the cost of capital
- Bboth assume reinvestment at the cost of capital
- CNPV assumes reinvestment at the cost of capital; IRR assumes reinvestment at the IRRCorrect
Explanation
NPV implicitly reinvests interim cash flows at the opportunity cost of capital, which is realistic. IRR implicitly reinvests at the project's own IRR, which can be unrealistically high. This is why IRR can mislead when rankings conflict.
Did you get it right without looking?
One question tells you little. A timed set on Capital Investments and Capital Allocation shows your real accuracy, how long you take and where you lose marks.
More Capital Investments and Capital Allocation questions
- Two mutually exclusive projects have conventional cash flows. Project X has a higher NPV at the company's cost of capital, while Project Y h…
- A project costs $100,000 today and is expected to produce cash inflows of $60,000 at the end of Year 1 and $60,000 at the end of Year 2. The…
- A company's analyst finds that actual cash flows from a completed project were well below the original forecast. The capital budgeting activ…
- A firm has capital of $500,000 available and evaluates three indivisible projects. Project X: investment $300,000, PV of future cash flows $…
- A firm is evaluating a project whose cash flows are in nominal terms and include expected inflation of 3% a year. The firm's nominal require…
- A company spent 2 million last year on a feasibility study for a new plant. The plant now has a positive NPV of 1.5 million before consideri…