CS Professional · Corporate Restructuring, Valuation and Insolvency · Pre-Packaged Insolvency Resolution Process
The resolution professional of Kaveri Textiles Ltd files a termination application under Section 54D(3) after no plan was approved. Within how many days of the date of that application must the Adjudicating Authority pass its order terminating the PIRP?
The Adjudicating Authority must pass the termination order within thirty days of the date of the resolution professional's application, as Section 54N(1) provides. The same order must also state how pending avoidance-transaction proceedings will continue.
- ASeven days
- BFourteen days
- CThirty daysCorrect
- DNinety days
Explanation
Section 54N(1) requires the Adjudicating Authority to pass the termination order within thirty days of the date of the application. The order also provides for the manner of continuation of avoidance-transaction proceedings.
Did you get it right without looking?
One question tells you little. A timed set on Pre-Packaged Insolvency Resolution Process shows your real accuracy, how long you take and where you lose marks.
More Pre-Packaged Insolvency Resolution Process questions
- Prakash Tools Pvt Ltd, an MSME, is in a pre-packaged insolvency resolution process (PIRP). The committee of creditors (CoC) has not approved…
- The Adjudicating Authority admits the pre-pack application of Bhoomi Agro Ltd. The application named an insolvency professional against whom…
- Sunrise Packaging Pvt Ltd, a company classified as a micro enterprise under the MSMED Act, 2006, has committed a default as defined in secti…
- The board of Meera Polymers Pvt Ltd has finalised a declaration under section 54A(2)(f) for a pre-pack. Which of the following content is co…
- During a PPIRP of Narmada Foods Pvt Ltd, before any plan is approved, the CoC votes to terminate the process and the RP informs the Adjudica…
- The Adjudicating Authority admits the pre-packaged insolvency application of Kaveri Engineering Ltd on 1 March. Till when does the order of …