CMA Final · Strategic Cost Management · Assignment
Three operators W1, W2 and W3 are available for four jobs J1 to J4; each operator can do only one job and one job will remain undone. Costs (₹ thousand) for J1, J2, J3, J4 are: W1: 10, 14, 12, 16; W2: 13, 11, 15, 14; W3: 12, 15, 11, 13. The unbalanced problem is balanced by adding a dummy operator with zero cost. What is the minimum total cost and which job is left unassigned?
The minimum cost is ₹32 thousand with J4 left unassigned. After adding a zero-cost dummy operator, the best allocation is W1 to J1 at 10, W2 to J2 at 11 and W3 to J3 at 11. Leaving out any other job costs at least 34 thousand.
- A₹32 thousand; J4 unassignedCorrect
- B₹34 thousand; J3 unassigned
- C₹35 thousand; J2 unassigned
- D₹36 thousand; J1 unassigned
Explanation
Adding a dummy row of zeros, the job given to the dummy is the one left undone. Best totals by omitted job are: J1 omitted 36 (W1-J3, W2-J2, W3-J4); J2 omitted 35 (W1-J1, W2-J4, W3-J3); J3 omitted 34 (W1-J1, W2-J2, W3-J4); J4 omitted 32 (W1-J1, W2-J2, W3-J3). The minimum is 32 with J4 unassigned.
Did you get it right without looking?
One question tells you little. A timed set on Assignment shows your real accuracy, how long you take and where you lose marks.
More Assignment questions
- A workshop has 4 machines and 3 jobs, and each job needs exactly one machine. The cost of doing each job on each machine is known. Which ste…
- A firm assigns three salesmen P, Q and R to three territories 1, 2 and 3, one each. Expected monthly profit in ₹ lakh is: P: 12, 10, 8; Q: 9…
- Three technicians A, B and C are to be assigned one each to three jobs J1, J2 and J3. The cost (₹ '000) is: A: 9, 11, 14; B: 12, 7, 10; C: 8…
- Three workers P, Q and R are to be assigned one each to Jobs 1, 2 and 3. Costs (₹) are: P: 12, 15, 10; Q: 14, 11, 16; R: 13, 17, 9. Worker R…
- Three machines M1, M2 and M3 must each be given one of four jobs a, b, c, d (one job per machine, one job remains unassigned). Costs (₹ '00)…
- Three workers W1, W2, W3 are available for four jobs J1 to J4, and each worker can take at most one job; one job stays unassigned. Costs (Rs…