CS Professional · Arbitration, Mediation and Conciliation · Emerging Aspects: Fast Track and Virtual Arbitration
Under a fast track agreement between Nilgiri Tea Estates and Sahyadri Traders, the sole arbitrator enters upon the reference on 1 March. The award is not made by 31 August. What follows under section 29B?
Sub-sections (3) to (9) of section 29A apply. Section 29B(4) requires the fast track award within six months of the tribunal entering upon the reference, and section 29B(5) states that on delay those provisions of section 29A govern, rather than automatic termination or a restart.
- AThe proceedings terminate automatically and the agreement is discharged
- BThe provisions of sub-sections (3) to (9) of section 29A apply to the proceedingsCorrect
- CThe parties must restart the arbitration as a regular one
- DThe arbitrator's fees become payable in full regardless of the delay
Explanation
Section 29B(4) requires the award within six months from the date the tribunal enters upon the reference. Under 29B(5), if it is not made in time, sub-sections (3) to (9) of section 29A apply. Termination is not automatic, and the section does not say the proceedings must restart.
Did you get it right without looking?
One question tells you little. A timed set on Emerging Aspects: Fast Track and Virtual Arbitration shows your real accuracy, how long you take and where you lose marks.
More Emerging Aspects: Fast Track and Virtual Arbitration questions
- Mehta Infra Ltd and Bharat Steel Ltd agree in writing to fast track arbitration. The tribunal enters upon the reference on 1 March. By which…
- Orion Infra Ltd (Mumbai) and Deccan Steel Ltd (Hyderabad) have not agreed on a seat for their arbitration. The sole arbitrator proposes to h…
- Under a fast track agreement, Gupta Foods Ltd wants an oral hearing but Bhatia Logistics objects, and the sole arbitrator sees no need for o…
- A sole arbitrator enters upon the reference in a fast track arbitration on 1 March. No award is made by 1 September of the same year, and no…
- Under a fast track arbitration agreement between Bharat Steel Ltd and Gomti Engineering Ltd, the parties have agreed on a sole arbitrator, M…
- Meera Textiles Pvt Ltd and Kaveri Dyes entered into a supply contract that has an arbitration clause. A dispute arises, and before any arbit…