ACCA Strategic Professional · Advanced Audit and Assurance (International) · Quality management (firm and engagement level)
Under ISQM 1, which statement best describes the firm's responsibility for engagement partner accountability for quality on an individual audit?
The engagement partner is responsible for managing and achieving quality on the individual engagement, while the firm is responsible for designing, implementing and operating its system of quality management. The engagement quality reviewer gives an objective evaluation but does not replace the partner's responsibility.
- AThe engagement partner is responsible for managing and achieving quality on the engagement, while the firm remains responsible for the system of quality managementCorrect
- BOnly the firm's leadership is responsible for quality, and the engagement partner has no responsibility
- CThe engagement quality reviewer is solely responsible for the quality of the engagement
- DThe client's audit committee is responsible for the quality of the engagement
Explanation
ISA 220 (Revised) makes the engagement partner responsible for overall quality on the engagement, including direction, supervision and review, while ISQM 1 makes the firm responsible for its system of quality management. The EQR provides an objective evaluation but does not take over the partner's responsibility, and the audit committee does not own audit quality.
Did you get it right without looking?
One question tells you little. A timed set on Quality management (firm and engagement level) shows your real accuracy, how long you take and where you lose marks.
More Quality management (firm and engagement level) questions
- During the audit of Brightwell Group, an EQR is appointed. The engagement partner wants to date the auditor's report on 12 March. The EQR ha…
- During an audit of Zenith Foods, the engagement partner finds the team lacks expertise in valuing complex biological assets. The firm has no…
- A national audit regulator inspects Brightwater & Co and reports that the firm's engagement files for three listed clients lacked sufficient…
- Quill Audit's engagement partner on a client assignment learns that a senior team member has serious concerns about the client's revenue rec…
- During a firm-wide review, Orchid LLP finds that several audit files were signed off with unresolved deficiencies in documenting going conce…
- Brightwell & Co, an audit firm, is designing its system of quality management under ISQM 1. The managing partner says that responsibility fo…