ACCA Applied Skills · Corporate and Business Law (Global) · Introduction to the UN Convention on Contracts for the International Sale of Goods and ICC Incoterms
Under the CISG, Tolland Ltd (buyer) has not paid the price when due for goods that Sarnia Co (seller) delivered. Sarnia gives Tolland a reasonable additional period of time to pay. What is the effect of this under the CISG?
During the extra period Sarnia cannot use inconsistent remedies such as avoiding the contract, unless Tolland declares it will not pay, though it keeps its right to damages for delay. If Tolland still fails to pay within the period, Sarnia may then avoid the contract.
- ASarnia loses all rights to claim damages
- BSarnia may not resort to any remedy for breach during that period, except claiming damages for delay, unless Tolland says it will not payCorrect
- CSarnia must immediately avoid the contract
- DThe contract automatically ends when the period expires
Explanation
Fixing an additional period (Nachfrist) means the seller cannot use remedies inconsistent with it during that period, but may still claim damages for delay. If the buyer does not pay within the period or declares it will not, the seller may avoid. Avoidance is not automatic.
Did you get it right without looking?
One question tells you little. A timed set on Introduction to the UN Convention on Contracts for the International Sale of Goods and ICC Incoterms shows your real accuracy, how long you take and where you lose marks.
More Introduction to the UN Convention on Contracts for the International Sale of Goods and ICC Incoterms questions
- Incoterms 2020 contains eleven rules, divided into two groups. Which description of the groups is correct?
- Kestrel Ltd (State A) agreed to sell machine parts to Bruna SA (State B). Both states are CISG contracting states and the contract does not …
- Mora Ltd sells specialised packaging to Nest Co under a CISG contract. Delivery is late by two weeks, but Nest still receives usable goods a…
- Jarrow Ltd (contracting state A) agrees to build and install a complete production line for Kestrel Ltd (contracting state B). Kestrel will …
- A seller in Kenya sells goods to a buyer in Spain on CIF Barcelona terms (Incoterms 2020). Which statement correctly describes the seller's …
- Ivor Ltd (State I) offers goods to Jaxon Co (State J), both CISG contracting states. Jaxon does not reply but begins to load the goods onto …