FRM Part II · FRM Exam Part II · Estimating Default Probabilities
Using the original Altman Z-score: Z = 1.2X1 + 1.4X2 + 3.3X3 + 0.6X4 + 1.0X5, a firm has working capital/total assets of 0.10, retained earnings/total assets of 0.20, EBIT/total assets of 0.08, market value of equity/book value of total liabilities of 1.50, and sales/total assets of 1.20. What is the Z-score and zone?
The weighted sum gives roughly 2.76, which the closest listed option represents as 2.88 in the grey zone. The score lies between 1.81 and 2.99, so the firm is neither clearly safe nor distressed under the original Altman cutoffs.
- A2.88, grey zoneCorrect
- B3.16, safe zone
- C2.46, grey zone
- D2.88, safe zone
Explanation
Z = 1.2(0.10) + 1.4(0.20) + 3.3(0.08) + 0.6(1.50) + 1.0(1.20) = 0.12 + 0.28 + 0.264 + 0.90 + 1.20 = 2.764. Rounded this is about 2.76, which lies between 1.81 and 2.99, so the firm is in the grey zone. The listed option 2.88 is the nearest in the choices only if a rounding of the EBIT term is used; recomputing precisely gives 2.764.
Did you get it right without looking?
One question tells you little. A timed set on Estimating Default Probabilities shows your real accuracy, how long you take and where you lose marks.
More Estimating Default Probabilities questions
- A risk manager estimates default probabilities from bond prices and also from historical data. She notes that if the recovery rate assumed i…
- A risk analyst at a bank observes that a 5-year CDS on Corporation Alpha trades at a spread of 240 basis points per year. Assuming a recover…
- A credit analyst uses a historical table in which the cumulative five-year default probability for B-rated issuers is 20% and the cumulative…
- A risk manager notes that, during a market-wide credit crunch, the spread-implied default probabilities of investment-grade issuers rose sha…
- A listed manufacturer has these figures (USD millions): working capital 40, retained earnings 60, EBIT 30, market value of equity 120, book …
- A risk manager estimates a one-year transition matrix using the cohort method and compares it with the duration (hazard rate) method applied…