CS Professional · Arbitration, Mediation and Conciliation · Emerging Aspects: Fast Track and Virtual Arbitration
Vidarbha Cement Ltd and Konkan Logistics Ltd opted for fast track arbitration. The tribunal entered upon the reference on 1 March. No award has been made by 1 September, and no extension has been granted. The respondent asks what follows. Which is correct under the Act?
The six-month fast track period has expired, so sub-sections (3) to (9) of Section 29A apply to the proceedings. The Act does not make the agreement lapse or the mandate continue without consequence; it routes the delay into the Section 29A extension and mandate provisions.
- AThe proceedings terminate automatically and the agreement lapses
- BThe six-month period under Section 29B(4) has expired, and sub-sections (3) to (9) of Section 29A apply to the proceedingsCorrect
- CThe tribunal's mandate continues indefinitely without any consequence
- DOnly sub-section (1) of Section 29A applies
Explanation
Section 29B(4) requires the award within six months from the date the tribunal enters upon the reference. Section 29B(5) states that if it is not made in time, sub-sections (3) to (9) of Section 29A apply. So the proceedings are not automatically terminated, and the Section 29A consequences, including extension and mandate provisions, apply.
Did you get it right without looking?
One question tells you little. A timed set on Emerging Aspects: Fast Track and Virtual Arbitration shows your real accuracy, how long you take and where you lose marks.
More Emerging Aspects: Fast Track and Virtual Arbitration questions
- Mehta Infra Ltd and Bharat Steel Ltd agree in writing to fast track arbitration. The tribunal enters upon the reference on 1 March. By which…
- Under a fast track agreement, Gupta Foods Ltd wants an oral hearing but Bhatia Logistics objects, and the sole arbitrator sees no need for o…
- A sole arbitrator enters upon the reference in a fast track arbitration on 1 March. No award is made by 1 September of the same year, and no…
- Meera Pharma and Zenith Distributors agreed to fast track arbitration. The tribunal entered upon the reference in January but no award was m…
- Meridian Textiles Pvt Ltd and Kaveri Dyes Ltd have a supply contract with an ordinary arbitration clause. After a payment dispute arises, bu…
- The agreement between Anand Pharma Ltd and Bhatia Logistics Ltd fixes Hyderabad as the place of arbitration and is silent on where the tribu…