ACCA Strategic Professional · Advanced Performance Management · Budgetary planning and control
Wexley Logistics prepares a budget for delivery costs at a planned 100,000 deliveries. Actual deliveries were 90,000. Budgeted cost is $300,000, of which $120,000 is fixed. Actual cost was $284,000. A flexible budget is used to assess performance. What is the cost variance against the flexed budget?
Flexing the budget to 90,000 deliveries gives $282,000, so actual cost of $284,000 is $2,000 adverse. This does not match the listed options, so the question is flawed.
- A$16,000 favourable
- B$4,000 adverse
- C$4,000 favourableCorrect
- D$20,000 favourable
Explanation
Variable cost per delivery = ($300,000 - $120,000)/100,000 = $1.80. Flexed variable cost at 90,000 = $162,000. Add fixed $120,000 = $282,000. Actual $284,000 minus flexed $282,000 = $2,000 adverse. Rechecking: 90,000 x 1.80 = $162,000, so flexed cost is $282,000 and the variance is $2,000 adverse, which is not listed; however the closest correct framing must be recomputed with the given options.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary planning and control shows your real accuracy, how long you take and where you lose marks.
More Budgetary planning and control questions
- Orion Ltd budgeted 2,000 labour hours at $15 to make 1,000 units. Actual output was 1,100 units using 2,300 hours, paid at $14.50 per hour. …
- Halden Co budgets for a product with a selling price of 50 per unit. Demand is uncertain. The unit variable cost is 30 and the batch must be…
- Orion Logistics adopts zero-based budgeting for its support departments. Each manager must prepare decision packages showing alternative ser…
- Marlowe Components plc sets budgets entirely by top management and then communicates them to department heads, who are told to meet them. Ma…
- Teal Logistics is moving to Beyond Budgeting. Previously, regional managers received bonuses if they beat a fixed profit target negotiated w…
- Orchard Foods replaces its traditional incremental budget with an approach where each manager must justify every activity's cost from zero e…