CA Intermediate · Cost and Management Accounting · Budgets and Budgetary Control
Which budget is prepared first when a firm identifies that its principal budget factor is a shortage of skilled labour, and the firm wishes to coordinate all other budgets around it?
The labour budget is prepared first. When skilled labour is the principal budget factor, it limits what the firm can produce and sell, so the labour budget is fixed first and all other budgets are coordinated around that constraint rather than starting with sales.
- ACash budget, because cash is the ultimate limiting resource
- BLabour budget, because the limiting factor is the starting point for preparing the other budgetsCorrect
- CMaster budget, because it summarises everything else
- DSales budget, always, irrespective of the limiting factor
Explanation
The principal budget factor is the constraint that limits activity. Here skilled labour is the constraint, so the labour budget is fixed first and the other budgets are built around it. Choosing the sales budget regardless of the limiting factor is wrong because sales is the starting point only when demand is the constraint.
Did you get it right without looking?
One question tells you little. A timed set on Budgets and Budgetary Control shows your real accuracy, how long you take and where you lose marks.
More Budgets and Budgetary Control questions
- A manufacturing firm in Pune prepares its budget for the coming year but, instead of starting afresh, takes the previous year's actual figur…
- Verma Ltd expects to sell 8,000 units in March and 10,000 units in April. Desired closing finished stock is 20% of the next month's sales. O…
- Kapoor Ltd plans to sell 8,000 units in a quarter. Opening finished stock is 1,200 units and the desired closing finished stock is 1,700 uni…
- A manufacturer prepares a 12-month budget. At the end of every month, the month just completed is dropped and a new month is added at the en…
- Kapoor Industries produces a single product. Budgeted production is 5,000 units needing 3 kg of material per unit at Rs 40 per kg. Opening m…
- Rajesh Textiles Ltd. prepares its budget for the coming year by starting afresh and justifying every item of expenditure from zero, irrespec…