ACCA Applied Knowledge · Management Accounting · Behavioural aspects of budgeting
Which budgeting approach is MOST likely to reduce budgetary slack because managers must justify every item of expenditure from scratch?
Zero-based budgeting is most likely to reduce slack. Every cost item must be justified from a zero base each period, so padded allowances are challenged. Incremental budgeting just uplifts prior figures, which carries existing slack forward unchallenged.
- AIncremental budgeting
- BZero-based budgetingCorrect
- CImposed budgeting based on last year's figures
- DFixed budgeting with a percentage uplift
Explanation
Zero-based budgeting requires each activity to be justified afresh, so inflated cost allowances inherited from previous periods are exposed. Incremental budgets simply add a percentage to past figures, carrying forward any existing slack.
Did you get it right without looking?
One question tells you little. A timed set on Behavioural aspects of budgeting shows your real accuracy, how long you take and where you lose marks.
More Behavioural aspects of budgeting questions
- A cost centre manager at Brindle Co has a controllable budget of $200,000 and actual controllable costs of $212,000. Allocated head office c…
- A company sets a bonus paid in full only if a manager's actual costs are at or below budget. Budgeted costs are $200,000. The manager privat…
- A manager is told to prepare a budget for her department without being consulted, and the targets are simply handed down by senior managemen…
- A company allows each department manager to help set the departmental budget that they will later be judged against. Which style of budget s…
- Which situation would make an imposed budgeting approach more appropriate than a participative one?
- A manager's department is expected to sell 10,000 units next year. The manager proposes a budget of 9,000 units, and a 10% reduction in the …