ACCA Applied Knowledge · Management Accounting · Budget preparation
Which budgeting approach requires every activity to be justified afresh for each budget period, starting from a zero base rather than from the previous period's spending?
Zero-based budgeting is the approach. It builds the budget from zero, so each activity must be justified in terms of its costs and benefits before resources are allocated, unlike incremental budgeting, which simply adjusts last period's figures for expected changes.
- AIncremental budgeting
- BZero-based budgetingCorrect
- CRolling budgeting
- DFlexible budgeting
Explanation
Zero-based budgeting starts from nothing and requires each activity's costs and benefits to be justified. Incremental budgeting instead adds an adjustment to the prior period's figures.
Did you get it right without looking?
One question tells you little. A timed set on Budget preparation shows your real accuracy, how long you take and where you lose marks.
More Budget preparation questions
- A company makes products X and Y. Machine hours are limited to 1,200 hours. X contributes $30 per unit and uses 2 machine hours per unit; Y …
- Kora Co budgets sales of 12,000 units. Production process has a normal loss: 10% of units started are lost in production, with output being …
- Which of the following is normally the FIRST budget prepared when sales demand is the principal budget factor?
- Brindle Ltd budgets production of 5,000 units next quarter, each needing 2 kg of material costing $6 per kg. Opening material inventory is 1…
- A company uses a rolling budget of four quarters, updated each quarter. The original annual budget for quarters 1 to 4 had direct labour of …
- Nimbus Co has a production budget based on a principal budget factor. Sales demand is 20,000 units, but skilled labour is limited to 30,000 …