Which of the following is a recognised limitation of Mendelow's power-interest matrix?
A key limitation is that the matrix looks only at power and interest, so it ignores the legitimacy and urgency of stakeholder claims. It can be used for internal and external stakeholders alike, and it does differentiate between levels of power.
- AIt does not address the legitimacy or urgency of stakeholder claimsCorrect
- BIt cannot be applied to external stakeholders
- CIt requires stakeholders to be ranked using only financial data
- DIt assumes all stakeholders have equal power
Explanation
The matrix considers only power and interest, so it does not capture legitimacy or urgency, which are covered in other models such as Mitchell, Agle and Wood. It applies to both internal and external stakeholders and explicitly distinguishes levels of power.
Did you get it right without looking?
One question tells you little. A timed set on Stakeholders in business organisations shows your real accuracy, how long you take and where you lose marks.
More Stakeholders in business organisations questions
- A listed company's directors reject a proposal to close a profitable but polluting plant, saying the law is met and their duty is only to ma…
- Using the Mendelow power/interest matrix, a pressure group has high interest in a company's pollution record but little power to influence i…
- Karta plc's board proposes to cut costs by closing a factory and moving production overseas. Shareholders expect higher profits, while the l…
- A board argues that investing in better employee training and supplier relationships, while reducing this year's profit, is consistent with …
- The directors of Marlow Co plan to close a factory and move production overseas. This will raise profit, but the local community will lose i…
- Under Mendelow's power-interest matrix, a pension fund holds a large shareholding in a company but takes little interest in day-to-day opera…