CA Intermediate · Cost and Management Accounting · Unit & Batch Costing
Which of the following is the most appropriate statement about the nature of batch costing?
In batch costing the whole batch is the cost unit, and the cost per unit is the total batch cost divided by the number of units in that batch. It is not costed unit by unit like job costing, nor averaged over continuous output like process costing.
- AA batch is treated as a single cost unit, and the cost per unit is found by dividing the total batch cost by the number of units in the batchCorrect
- BEach unit in a batch is costed separately because every unit is made to a different customer specification
- CCosts are accumulated for each department for a period and averaged over the continuous output of that period
- DCosts are collected only for the sale of goods, and no cost is ascertained for production
Explanation
In batch costing a group of identical units is produced together and the batch is the cost unit. Total batch cost is divided by units in the batch to get unit cost. Option B describes job costing, and option C describes process costing.
Did you get it right without looking?
One question tells you little. A timed set on Unit & Batch Costing shows your real accuracy, how long you take and where you lose marks.
More Unit & Batch Costing questions
- A firm produces 250 units in a batch. Direct materials for the batch are ₹30,000 and direct labour is ₹20,000. Overheads are absorbed at 60%…
- A cement tile factory in Jaipur makes a single standard product and uses unit costing. For a month, the total production cost was ₹6,48,000 …
- Which of the following best describes the situation in which batch costing is the appropriate costing method?
- A manufacturer makes 2,000 units per batch. For one batch, the prime cost is Rs 3,20,000. Factory overheads are absorbed at 25% of prime cos…
- Sharma Pens Ltd manufactures a batch of 2,000 pens. Direct materials cost Rs 40,000 and direct wages Rs 24,000. Factory overheads are absorb…
- Sundaram Cement Works produced 20,000 tonnes in a quarter. Costs were: raw materials ₹12,00,000; direct wages ₹4,00,000; factory overheads ₹…