CS Professional · Insolvency and Bankruptcy - Law and Practice · Winding-Up by Tribunal
While an investigation under section 210 into Deccan Pharma Ltd is pending, the company proposes to dismiss a senior employee, Ms. Iyer. It applies to the Tribunal for approval and receives no response for thirty days from the application. What can the company do under section 218?
The company may proceed with the proposed action. Section 218(2) allows it to act against the employee if it does not receive the Tribunal's approval within thirty days of making the application. Appeal to the Appellate Tribunal arises only against an objection raised by the Tribunal.
- ADismiss her only after the Appellate Tribunal confirms the action
- BDismiss her immediately, as no objection was raised and she has no remedy
- CNot dismiss her until the investigation ends, whatever the Tribunal's silence
- DProceed with the proposed action, since only if no approval is received within thirty days of the application may the company take the actionCorrect
Explanation
Under section 218(2), if the company does not receive the Tribunal's approval within thirty days of making the application, then and only then may it proceed with the proposed action. Appellate Tribunal appeal arises only if the Tribunal sends an objection and the company is dissatisfied. Nothing bars action until investigation ends.
Did you get it right without looking?
One question tells you little. A timed set on Winding-Up by Tribunal shows your real accuracy, how long you take and where you lose marks.
More Winding-Up by Tribunal questions
- Udaan Logistics Ltd is being wound up by the Tribunal. Which of the following events, occurring after the petition was presented and without…
- During winding up of Sagar Metals Ltd by the Tribunal, the Company Liquidator reports that the former promoters committed fraud in respect o…
- Kaveri Textiles Ltd's winding-up petition before the Tribunal was presented on 1 June. On 15 June, its director sold a factory plot to Sande…
- A winding up petition against Sundaram Realty Ltd was presented to the Tribunal on 10 March. The Tribunal passed the winding up order on 25 …
- Kaveri Pumps Ltd transferred a plot of land to its promoter's relative for a nominal sum eight months before a winding-up petition was prese…
- A winding-up petition against Kaveri Textiles Ltd is pending before the Tribunal while an inspector is investigating the company. The Tribun…