Yamuna Constructions has a contract for Rs 50 lakh. Costs incurred to date are Rs 20 lakh, estimated further cost is Rs 40 lakh. In the first year, 33.33% complete is not relied on; under AS 7, the expected loss on the contract should be recognised:

The full expected loss of Rs 10 lakh is recognised immediately as an expense. Total expected cost is Rs 60 lakh against contract revenue of Rs 50 lakh. AS 7 requires foreseeable losses to be recognised at once, regardless of the stage of completion or work done.

  1. ARs 10 lakh as an expense immediately in fullCorrect
  2. BRs 10 lakh only in the year the contract is completed
  3. CRs 3.33 lakh in proportion to the stage of completion
  4. DNot at all until the contract is completed

Explanation

Total expected cost = 20 + 40 = Rs 60 lakh against revenue of Rs 50 lakh, giving an expected loss of Rs 10 lakh. AS 7 requires the entire expected loss to be recognised as an expense immediately, irrespective of the stage of completion.