ACCA Strategic Professional · Advanced Performance Management · Non-financial performance measurement
Zentra Ltd rewards its divisional managers solely on annual return on investment (ROI). A divisional manager declines a new project whose return is 14%, because the division's current ROI is 20%, even though the company's cost of capital is 10%. Which limitation of financial performance measures does this best illustrate?
The manager is showing dysfunctional behaviour: rejecting a project returning 14% against a 10% cost of capital to protect divisional ROI. The measure drives decisions that conflict with the group's goal of maximising value, which is a classic limitation of purely financial measures.
- ADysfunctional behaviour caused by a measure that conflicts with overall corporate goalsCorrect
- BInability of financial measures to be expressed in monetary terms
- CLack of objectivity because ROI is based on subjective estimates of customer opinion
- DExcessive reliance on external benchmarks rather than internal targets
Explanation
The project earns 14%, above the 10% cost of capital, so it would add value for the company. Rejecting it protects the manager's divisional ROI and bonus, which is goal incongruence. The other options describe features that do not apply to ROI.
Did you get it right without looking?
One question tells you little. A timed set on Non-financial performance measurement shows your real accuracy, how long you take and where you lose marks.
More Non-financial performance measurement questions
- Orion Software reports strong profit this year, but customer complaints are rising, key developers are leaving and few new products are in d…
- Halden Retail's board compares two frameworks. Its Balanced Scorecard has four perspectives. The board wants a framework that explicitly mea…
- Karvale Bank has set a scorecard objective of cutting loan approval time from 10 days to 3 days. Management believes this will raise custome…
- Quillon Bank's internal business process perspective currently measures cost per transaction only. Management wants a measure that captures …
- Orlando Pharma uses a quality measure: defects found per 1,000 units. Last year production was 2,400,000 units with 7,200 defects found at f…
- Hollis Pharma is judged by its board on short-term earnings per share. Its research division has a pipeline of drugs with uncertain but pote…