Zeta Co budgeted to produce 5,000 units using 2 kg of material per unit at a standard price of $4 per kg. Actual output was 5,200 units, using 10,600 kg of material that cost $44,520. What is the material price variance?

The material price variance is $2,120 adverse. Actual purchases of 10,600 kg should have cost $42,400 at the standard $4 per kg, but actually cost $44,520. Paying more than standard for the quantity bought gives an adverse price variance.

  1. A$2,120 adverseCorrect
  2. B$2,120 favourable
  3. C$1,000 adverse
  4. D$1,000 favourable

Explanation

Actual quantity at standard price = 10,600 x $4 = $42,400. Actual cost is $44,520. Difference = $2,120, and actual cost is higher, so the variance is adverse. The $1,000 figures come from the usage variance wrongly treated as price.

Did you get it right without looking?

One question tells you little. A timed set on Monitoring performance and reporting shows your real accuracy, how long you take and where you lose marks.

More Monitoring performance and reporting questions