FRM Part II · FRM Exam Part II · Risk Mitigation
A bank assesses a process with inherent annual expected loss of USD 8.0 million. Two independent controls each reduce the loss frequency by the stated effectiveness: control A is 60% effective and control B is 50% effective. Assuming the effects multiply, and a third assessment shows control B actually operates effectively only 80% of the time (so its effective reduction is 50% x 0.8), what is the residual expected loss?
Residual expected loss is USD 1.92 million. Control B's effective reduction is 50% x 0.8 = 40%, so residual equals 8.0 x 0.4 x 0.6. Ignoring the operating-effectiveness adjustment would understate the residual loss.
- AUSD 1.28 million
- BUSD 1.92 millionCorrect
- CUSD 0.80 million
- DUSD 2.40 million
Explanation
Control B's effective reduction is 0.5 x 0.8 = 40%. Residual = 8.0 x (1 - 0.6) x (1 - 0.4) = 8.0 x 0.4 x 0.6 = 1.92 million. Using the stated 50% gives 1.6 million, and the 1.28 million option wrongly applies 0.8 as a further multiplier on the pass-through (8 x 0.4 x 0.5 x 0.8 = 1.28 is not the correct adjustment).
Did you get it right without looking?
One question tells you little. A timed set on Risk Mitigation shows your real accuracy, how long you take and where you lose marks.
More Risk Mitigation questions
- A bank's payments platform supports a critical business service. Management sets a statement of the maximum disruption it is willing to tole…
- A bank outsources its payment processing to a single provider. Risk management is concerned that a failure of the provider would halt paymen…
- In the three lines model commonly applied by banks, a business unit's head of operations identifies, owns and tests the day-to-day controls …
- A bank's operational risk team is evaluating whether to buy insurance against losses from employee theft and fraud. Which feature of insuran…
- A bank's board is setting its operational resilience framework. It identifies critical operations and sets an impact tolerance for each. Whi…
- A bank wants to reduce its capital requirement by recognizing insurance as a mitigant under an advanced internal modelling approach. Which f…