A bank plans to outsource its payment-processing operations to a vendor. The bank's board asks who remains ultimately accountable to customers and regulators for the outsourced activity. Which answer is correct under standard supervisory guidance on outsourcing risk?
The bank's board and senior management remain ultimately accountable. Outsourcing transfers the performance of an activity, not responsibility for it, so the bank must still oversee the vendor and answer to customers and regulators for any failures in the outsourced service.
- AThe vendor, because it performs the activity day to day
- BThe bank's board and senior management, because outsourcing does not transfer accountabilityCorrect
- CThe vendor's external auditor, because it attests to the vendor's controls
- DThe regulator, because it approved the outsourcing arrangement
Explanation
Supervisory guidance states that outsourcing an activity does not relieve the bank's board and senior management of responsibility for it. The vendor performs the work but accountability stays with the bank. Regulators approving or being notified of an arrangement does not shift responsibility, and auditors only provide assurance.
Did you get it right without looking?
One question tells you little. A timed set on Risk Mitigation shows your real accuracy, how long you take and where you lose marks.
More Risk Mitigation questions
- A bank's payments platform supports a critical business service. Management states that the service must be restored within 4 hours of a dis…
- A global bank relies on one cloud provider for its card authorisation service. A resilience review finds that both the primary and backup en…
- A bank faces a low-frequency, high-severity risk of a data center fire. It buys property insurance with a large deductible and also builds a…
- A bank tests its continuity plan for a critical clearing function. The plan relies on a nearby secondary site and on the same regional power…
- Which contractual provision best supports a bank's ability to oversee an outsourced critical service on an ongoing basis?
- A bank's expected annual loss from a process is USD 4 million with an event frequency of 20 per year. A new control is projected to cut freq…