FRM Part I · FRM Exam Part I · Calculating and Applying VaR
A bank uses basic historical simulation with a 250-day window. The 95% 1-day VaR is taken as the 13th-worst loss, since 5% of 250 is 12.5 and the convention rounds up. Which statement about this estimate is most accurate?
The estimate is nonparametric and weights all 250 observations equally, so it adapts slowly to changes in volatility. It does not assume normality or rely only on a mean and standard deviation, and shortening the window to 50 days would make tail estimation less precise.
- AIt assumes returns are normally distributed with constant volatility
- BIt uses only the mean and standard deviation of the historical sample
- CIt is a nonparametric estimate that gives equal weight to all 250 observations and is slow to react to volatility changesCorrect
- DIt becomes more precise as the window is shortened to 50 days
Explanation
Basic historical simulation is nonparametric, makes no normality assumption, and weights all observations equally, so it reacts slowly to volatility shifts. Shortening the window reduces the number of tail observations and raises sampling error rather than improving precision.
Did you get it right without looking?
One question tells you little. A timed set on Calculating and Applying VaR shows your real accuracy, how long you take and where you lose marks.
More Calculating and Applying VaR questions
- A portfolio has a delta-equivalent exposure of +2,000 units of an underlying asset and a gamma of -300 per $ (change in delta per $1 move). …
- A trader holds a call option with delta 0.60 on 10,000 shares of a stock priced at USD 50. The stock's daily volatility is 2%. Using the del…
- Which of the following is a correct statement about the parameters used to specify a VaR measure?
- A risk manager simulates a two-asset portfolio using Monte Carlo with correlated normal returns. Asset volatilities are 20% and 30% with cor…
- A risk manager compares methods for a portfolio that is short a large number of options and so has substantial negative gamma, with a large …
- A risk manager uses the delta-normal method to estimate the one-day VaR of a portfolio consisting only of long positions in call options on …