A bank's disaster recovery test shows that its trading system, supported by a secondary data center, recovers in 6 hours. The business continuity plan assumes recovery within 3 hours. A manager proposes simply documenting the 6-hour result as the new target without changes. Which response is most consistent with sound resilience practice?

The firm should compare the 6-hour result with the service's impact tolerance and, if it breaches it, fix the gap or escalate for a formal risk acceptance decision. Simply relabeling the target conceals a weakness, and insurance cannot restore a disrupted critical service.

  1. ACompare the 6-hour result with the impact tolerance, and if it exceeds it, remediate the gap or escalate for a risk acceptance decisionCorrect
  2. BAccept 6 hours as the new RTO because tests always differ from live events
  3. CDiscard the test result as unrepresentative and rely on the original plan
  4. DTransfer the whole risk by raising insurance coverage, which removes the need for recovery

Explanation

A test gap should be assessed against the impact tolerance and business need. If the actual capability breaches it, management must remediate or formally escalate and accept the risk. Silently resetting the target hides the weakness, and insurance does not restore service.