FRM Part II · FRM Exam Part II · Early Warning Indicators
A bank's treasury team tracks an early warning indicator (EWI) dashboard for liquidity risk. The Chief Risk Officer asks why the dashboard includes both internal indicators (such as deposit outflow rates) and external indicators (such as sovereign CDS spreads). Which is the best justification?
The best justification is that internal indicators reveal bank-specific vulnerabilities, while external indicators reveal market-wide or systemic stress. Using both gives wider coverage of potential liquidity stress sources. Neither type replaces stress testing, contingency funding plans, thresholds or escalation procedures.
- AExternal indicators are always more accurate than internal indicators, so internal ones are kept only for regulatory reporting
- BInternal indicators capture bank-specific vulnerabilities while external indicators capture market-wide or systemic stress, so together they give broader coverageCorrect
- CInternal indicators replace the need for stress testing, while external indicators replace contingency funding plans
- DUsing both types removes the need to set thresholds or escalation procedures
Explanation
Internal indicators reflect the bank's own funding and asset quality conditions, while external indicators reflect market or systemic conditions. Combining them provides wider coverage of possible liquidity stress sources. The other options claim substitution or accuracy that the indicators do not provide.
Did you get it right without looking?
One question tells you little. A timed set on Early Warning Indicators shows your real accuracy, how long you take and where you lose marks.
More Early Warning Indicators questions
- A bank sets a green/amber/red framework for its EWIs. The wholesale funding rollover rate falls into amber. Which governance response is mos…
- A bank monitors the ratio of wholesale funding to total funding. Over the past 24 months the ratio had mean 30% and standard deviation 4%. M…
- A bank's liquidity risk team classifies its monitoring metrics. Which of the following is best classified as an external (market-based) earl…
- A risk manager reviews an EWI whose red threshold is set at the historical 99th percentile of the indicator. Over the past three years it ha…
- A bank's liquidity committee wants an EWI set that gives both early detection and few false alarms. Which design choice is most consistent w…
- A bank's treasury team is designing an early warning indicator (EWI) framework for liquidity risk. Which description best captures the prima…