CMA Intermediate · Cost Accounting · Batch Costing
A batch of 2,000 units is completed. 100 units are found defective and are reworked at an extra cost of ₹15,000. The defects arise normally in this type of work and are not due to a specific batch. As per usual cost accounting treatment, the rework cost should be:
Rework cost on defectives that arise normally in the course of operations is charged to factory overheads and absorbed across all jobs and batches. It is charged to a particular batch only when the defects are specific to that batch.
- ACharged to the Costing Profit and Loss Account
- BCharged to the batch as part of its cost
- CCharged to factory overheads and absorbed over all jobs and batchesCorrect
- DDeducted from the sales price of the batch
Explanation
Rework cost on defectives that is normal and general to the process is treated as factory overhead, spread over all production. It is charged to a specific batch only if the defects are due to that batch's special requirements. Abnormal rework goes to Costing P&L.
Did you get it right without looking?
One question tells you little. A timed set on Batch Costing shows your real accuracy, how long you take and where you lose marks.
More Batch Costing questions
- Which statement about the features of batch costing is correct?
- Which of the following is the most appropriate treatment of the cost of a special tool made exclusively for one batch and scrapped after its…
- Kaveri Auto Components makes a batch of 500 gear sets. Batch costs: materials ₹1,20,000, direct wages ₹60,000, and set-up cost ₹15,000 incur…
- Under batch costing, the Economic Batch Quantity (EBQ) is the batch size that minimises the sum of:
- In batch costing, a batch of 500 units is produced for a specific customer order. Spoilage that is normal and arises due to the nature of th…
- In batch costing, the Economic Batch Quantity (EBQ) is the batch size that: