FRM Part II · FRM Exam Part II · Risk Mitigation
A broker-dealer runs a business impact analysis for its trade settlement function. Management finds that the function's RTO of 8 hours is shorter than the 12 hours the backup data-centre vendor contractually needs to bring the environment online. What is the most appropriate response?
The bank should close the gap by upgrading recovery capability, such as a warm standby or revised vendor terms, or have senior management formally accept the residual risk. Ignoring the mismatch, quietly lengthening the RTO or dropping the function from scope would leave a critical process exposed.
- AKeep the 8-hour RTO and document it as met, since the contract is a vendor issue
- BLengthen the RTO to 12 hours without further review, since the contract is binding
- CClose the gap by improving recovery capability, such as a warm standby or renegotiated vendor terms, or by formally escalating acceptance of the residual riskCorrect
- DRemove the settlement function from the plan's scope until the vendor is replaced
Explanation
A gap between required and achievable recovery times must be addressed: either strengthen capability or have senior management knowingly accept the residual risk. Reporting the RTO as met is wrong, silently relaxing it ignores business needs, and excluding a critical function undermines the plan.
Did you get it right without looking?
One question tells you little. A timed set on Risk Mitigation shows your real accuracy, how long you take and where you lose marks.
More Risk Mitigation questions
- A bank considers insurance mitigation under an advanced measurement approach-style framework. A risk manager notes that the insurance policy…
- A bank's security architecture assumes no user or device is trusted by default, even inside the corporate network, and requires continuous v…
- A risk manager compares two mitigation options for a fraud risk with expected annual loss of USD 2.0 million. Option A costs USD 0.6 million…
- A bank's ransomware scenario shows an annual probability of 5% and a loss of USD 40 million if it occurs. Management considers two options. …
- A bank estimates that, without a new email-filtering control, phishing-related losses would have an expected annual loss of USD 4.0 million.…
- A bank considers shifting part of its cyber risk to a captive insurance subsidiary that reinsures with external markets. Which statement bes…