A callable bond has a Z-spread of 120 bps and an OAS of 70 bps, computed using the same benchmark curve. A portfolio manager asks what the 50 bps difference represents. Which interpretation is correct?

The 50 bps difference is the option cost: the investor is short the call to the issuer. The Z-spread ignores option exercise and so includes compensation for it, while the OAS strips it out, leaving the spread for credit and liquidity risk.

  1. ACompensation for the credit risk of the issuer that the OAS ignores
  2. BThe cost of the embedded call option borne by the investor, expressed in spread termsCorrect
  3. CThe liquidity premium that is included in the OAS but not in the Z-spread
  4. DThe value of the investor's put option to the issuer

Explanation

The Z-spread discounts cash flows to maturity along the curve without accounting for exercise of the option, so it includes compensation for the option. The OAS removes option value, leaving the spread for credit and liquidity risk. The difference, 120 minus 70 = 50 bps, is the option cost to the investor who is short the call.