CMA Intermediate · Operations Management and Strategic Management · Operations Planning

A Chennai auto-component firm recorded demand for the last three months as: April 400 units, May 440 units, June 480 units. Using a 3-month simple moving average, what is the forecast for July?

The July forecast is 440 units. A 3-month simple moving average adds the three months' demand (400 + 440 + 480 = 1,320) and divides by three. This gives equal weight to each month and does not project the upward trend.

  1. A480 units
  2. B460 units
  3. C440 unitsCorrect
  4. D520 units

Explanation

Simple moving average = (400 + 440 + 480)/3 = 1,320/3 = 440 units. Choosing 480 uses only the latest month (naive forecast). Choosing 520 extends the trend, which a moving average does not do. Choosing 460 is the average of May and June only, ignoring April.

Did you get it right without looking?

One question tells you little. A timed set on Operations Planning shows your real accuracy, how long you take and where you lose marks.

More Operations Planning questions