A firm uses a level (steady) production strategy in aggregate planning to meet seasonal demand. Which statement is correct about this strategy?
Under a level production strategy, output and workforce stay constant, and inventory built in slack periods or backlogs absorb the fluctuations in demand. Changing workforce each month is the chase strategy, and level strategy actually increases inventory holding costs.
- AWorkforce size is changed every month to match demand
- BOutput is kept constant, and inventory or backlogs absorb demand fluctuationsCorrect
- CIt eliminates all inventory holding costs
- DIt requires frequent overtime and subcontracting in peak months
Explanation
Under level strategy output rate and workforce stay constant; stock builds in low-demand periods and is used in peak periods, or backorders occur. Changing workforce monthly is the chase strategy. Inventory costs are not eliminated; they rise.
Did you get it right without looking?
One question tells you little. A timed set on Operations Planning shows your real accuracy, how long you take and where you lose marks.
More Operations Planning questions
- A Surat firm's forecasts and actual demand for four months were: Month 1 forecast 100, actual 110; Month 2 forecast 120, actual 110; Month 3…
- In a product (line) layout, work stations are arranged in the sequence of operations. Which of the following is a recognised characteristic …
- Which capacity strategy builds capacity ahead of anticipated demand, accepting some idle capacity in the early period?
- A Chennai auto-component firm recorded demand for the last three months as: April 400 units, May 440 units, June 480 units. Using a 3-month …
- Which statement about the time fences used in a Master Production Schedule is correct?
- A Jaipur textile unit uses single exponential smoothing with alpha = 0.3. Its forecast for the last month was 200 units and the actual deman…