CMA Final · Strategic Cost Management · Learning Curve
A Chennai firm uses a 90% learning curve (cumulative average model) with y = a x^b, where b = -0.152. The first batch took 1,000 hours. Cumulative average time for 8 batches is closest to:
The cumulative average time for eight batches is 729 hours. Eight units equal three doublings of output, and each doubling multiplies the cumulative average by 0.90, so 1,000 x 0.9 x 0.9 x 0.9 gives 729.
- A810 hours
- B900 hours
- C729 hoursCorrect
- D656 hours
Explanation
8 batches is three doublings, so the average = 1,000 x 0.9^3 = 729 hours. Option 810 applies only two doublings. Option 656 applies four doublings.
Did you get it right without looking?
One question tells you little. A timed set on Learning Curve shows your real accuracy, how long you take and where you lose marks.
More Learning Curve questions
- A firm records that the first unit of a job took 100 hours and the first 4 units together took 324 hours. Assuming a cumulative average lear…
- Meera Engineering uses an 80% cumulative average learning curve. The first unit needs 50 hours and labour costs Rs 120 per hour. What is the…
- A Chennai firm expects a 90% cumulative average learning curve. The first unit of a product needs 100 labour hours at ₹100 per hour. What is…
- A Pune firm's first unit of a new machine took 800 labour hours. The production process follows an 80% cumulative average time learning curv…
- Kaveri Textiles completed its first batch of a new garment in 200 hours. After the first 8 batches, the total time taken was 1,166.4 hours. …
- A Chennai manufacturer's production follows an 80% cumulative average-time learning curve. The first unit takes 10 hours. How many hours wil…