Skip to content

CMA Final · Strategic Cost Management · Learning Curve

A Chennai firm uses a 90% learning curve (cumulative average model) with y = a x^b, where b = -0.152. The first batch took 1,000 hours. Cumulative average time for 8 batches is closest to:

The cumulative average time for eight batches is 729 hours. Eight units equal three doublings of output, and each doubling multiplies the cumulative average by 0.90, so 1,000 x 0.9 x 0.9 x 0.9 gives 729.

  1. A810 hours
  2. B900 hours
  3. C729 hoursCorrect
  4. D656 hours

Explanation

8 batches is three doublings, so the average = 1,000 x 0.9^3 = 729 hours. Option 810 applies only two doublings. Option 656 applies four doublings.