Kaveri Textiles completed its first batch of a new garment in 200 hours. After the first 8 batches, the total time taken was 1,166.4 hours. Assuming a cumulative average time learning curve, what is the learning rate?

The learning rate is 90%. The cumulative average for eight batches is 145.8 hours, which is 0.729 of the 200-hour first batch. Eight batches involve three doublings, and the cube root of 0.729 is 0.90, so the curve is a 90% learning curve.

  1. A80%
  2. B85%
  3. C90%Correct
  4. D95%

Explanation

Cumulative average for 8 batches = 1,166.4 / 8 = 145.8 hours. Ratio to the first batch = 145.8 / 200 = 0.729. Since 8 batches means three doublings, r^3 = 0.729, so r = 0.90. An 80% rate would give 0.512, i.e. 102.4 hours, which does not match the data.