A company is value engineering a product with a target selling price of $80 and a required profit margin of 25% of selling price. The current estimated cost is $68. Cost reduction identified so far from the redesign is $5. What further cost saving is needed to reach the target cost?

A further $3 saving is needed. Target cost is $80 minus a 25% margin of $20, giving $60. The current cost of $68 is $8 too high, and the $5 already identified leaves a remaining gap of $3.

  1. A$3Correct
  2. B$8
  3. C$13
  4. D$5

Explanation

Target cost = 80 less 25% margin ($20) = $60. Current cost is $68, so total reduction needed is $8. Identified savings are $5, leaving $3 still required. Option B ignores the $5 already found, and option C subtracts incorrectly from the price.

Did you get it right without looking?

One question tells you little. A timed set on Cost reductions and value enhancement shows your real accuracy, how long you take and where you lose marks.

More Cost reductions and value enhancement questions