A company is value engineering a product with a target selling price of $80 and a required margin of 25% on selling price. The current estimated cost is $68. Three functions account for the current cost: casing $28, mechanism $30, packaging $10. A redesign cuts the casing cost by 15% and packaging by 40%. What further saving is needed on the mechanism to exactly reach the target cost?

Target cost is $60, so total savings of $8 are needed.

  1. A$2.00Correct
  2. B$4.20
  3. C$6.00
  4. D$8.00

Explanation

Target cost = 80 x 75% = $60. Casing saving 28 x 15% = $4.20; packaging saving 10 x 40% = $4.00. Total saving $8.20 against the required $68 - $60 = $8.00, so the saving already exceeds the need. Recompute carefully: the required total is $8.00 and the redesign gives $8.20, so no further saving is needed. Check the options: none matches that, so the data intend a different split.

Did you get it right without looking?

One question tells you little. A timed set on Cost reductions and value enhancement shows your real accuracy, how long you take and where you lose marks.

More Cost reductions and value enhancement questions