ACCA Applied Knowledge · Management Accounting · Behavioural aspects of budgeting
A company uses a bonus scheme paying a manager 10% of any favourable variance on the sales budget. The budgeted sales are $500,000, set after the manager's estimate. The manager expects to achieve $540,000 if she works normally. Which combination best describes the likely behaviour and its effect?
She is likely to propose a lower budget, such as $450,000, because the bonus is a percentage of the favourable variance. A lower target gives a larger variance and bonus, so the scheme rewards slack instead of accurate estimates.
- AShe will propose a budget close to $540,000 because this maximises her bonus
- BShe will propose a lower budget such as $450,000, because this increases the favourable variance and the bonus, and the scheme encourages slackCorrect
- CShe will propose a higher budget because the bonus rises with the target
- DShe will be indifferent because the bonus is a fixed percentage
Explanation
When the bonus depends on beating a budget she helps set, she gains from a low target. At $450,000 her expected favourable variance is $90,000 and bonus $9,000, against $0 if the budget were $540,000. Therefore the scheme encourages slack and undermines accurate budgeting.
Did you get it right without looking?
One question tells you little. A timed set on Behavioural aspects of budgeting shows your real accuracy, how long you take and where you lose marks.
More Behavioural aspects of budgeting questions
- Which of the following is a likely negative consequence of budgetary slack for an organisation?
- A company wants its budget targets to motivate managers. Which approach is most likely to achieve this according to accepted behavioural the…
- A department manager's budgeted expenditure for the year is $200,000. Her bonus is paid only if actual spending does not exceed budget. Near…
- A company finds that its managers spend all of their allocated budget each year, even when they could save money, because they fear next yea…
- Which budget-setting approach is MOST likely to encourage budgetary slack?
- A manager is told by senior management to meet a budget that has been set entirely without any input from her or her team. Which behavioural…