ACCA Applied Knowledge · Management Accounting · Alternative cost accounting principles
A company uses target costing for a new product. Which action would most directly help close a cost gap before production starts?
Value engineering is the most direct way, because it redesigns the product or its components to remove cost that customers do not value, closing the gap between estimated cost and target cost without changing the market-determined price.
- AValue engineering to remove unnecessary features from the designCorrect
- BRaising the selling price after launch to recover the shortfall
- CAbsorbing the gap into factory overheads over several periods
- DDelaying all marketing spend until the maturity stage
Explanation
Target costing starts from the market price and required margin, then reduces cost to reach the target. Value engineering redesigns the product to cut cost while keeping value to the customer. Raising price contradicts the market-set price premise.
Did you get it right without looking?
One question tells you little. A timed set on Alternative cost accounting principles shows your real accuracy, how long you take and where you lose marks.
More Alternative cost accounting principles questions
- Which one of the following is how throughput is defined in throughput accounting?
- Which of the following is most likely to make ABC more suitable than traditional absorption costing for an organisation?
- Zeta Co produced 12,000 units and sold 13,500 units in a period. Fixed production overhead is budgeted at $96,000 for a normal output of 12,…
- Which of the following best describes target costing?
- Which of the following is a feature of life cycle costing?
- Which statement best describes life cycle costing?