A company's budget for a period was 5,000 units of output at a total cost of $60,000, of which $20,000 is fixed. Actual output was 5,500 units. What is the flexed budget cost allowance for the actual output?

The flexed budget cost is $64,000. Fixed costs stay at $20,000 while variable costs of $8 per unit are applied to 5,500 units, giving $44,000. Scaling the whole $60,000 up would wrongly flex the fixed cost as well.

  1. A$60,000
  2. B$66,000
  3. C$64,000Correct
  4. D$68,000

Explanation

Variable cost per unit = ($60,000 - $20,000) / 5,000 = $8. Flexed cost = $20,000 + (5,500 x $8) = $20,000 + $44,000 = $64,000. Scaling the total cost ($66,000) wrongly treats fixed cost as variable.