ACCA Applied Knowledge · Management Accounting · Budgetary control and reporting
Which of the following is the most appropriate treatment in a budgetary control report when a cost variance arises from a supplier price rise across the whole market, which the budget holder could not have avoided?
The variance should be identified as uncontrollable by the budget holder and reported separately, with possible budget revision. This avoids unfairly blaming the manager while still giving senior management information about the market price rise.
- AReport it as adverse and hold the budget holder fully accountable
- BRemove it from the budget holder's report and investigate nothing
- CIdentify it as uncontrollable by the budget holder and report it separately, possibly revising the budgetCorrect
- DTreat it as a favourable variance because prices are higher
Explanation
Uncontrollable variances should be separated so the manager is not judged on them, but still reported to higher management for action such as budget revision or pricing decisions. Ignoring it entirely loses information.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary control and reporting shows your real accuracy, how long you take and where you lose marks.
More Budgetary control and reporting questions
- Budgeted sales were 5,000 units at $20 each. Actual sales were 5,400 units at $19 each. Budgeted variable cost is $12 per unit. What is the …
- Vega Ltd's Department X had a budget of $200,000 and actual costs of $236,000, including $15,000 of central service charges that were $6,000…
- Which item should normally be excluded from a budget report used to assess a department manager's performance?
- Budgeted production at Orion Ltd was 10,000 units, with fixed overheads of $80,000 and variable overheads of $3 per unit. Actual production …
- Budgeted sales were 10,000 units at $20 each. Actual sales were 11,000 units at $19 each. Budgeted variable cost is $12 per unit; fixed cost…
- A company's fixed budget for a period was based on 10,000 units, with total budgeted costs of $150,000. Actual output was 11,000 units. Whic…