ACCA Applied Knowledge · Management Accounting · Cost reductions and value enhancement
A council spent $240,000 on a training programme and delivered 1,600 training hours against a plan of 2,000 hours at a budget of $250,000. Which statement is correct about the cost per training hour?
Actual cost was $150 per training hour (240,000/1,600) against a plan of $125 (250,000/2,000). Since each unit of output cost more than planned, the programme was less efficient, even though total spending was below budget.
- AActual $150 per hour versus planned $125 per hour, so the programme was less efficient than plannedCorrect
- BActual $150 per hour versus planned $125 per hour, so the programme was more economical than planned
- CActual $120 per hour versus planned $125 per hour, so the programme was more efficient than planned
- DActual $150 per hour versus planned $120 per hour, so the programme was less efficient than planned
Explanation
Actual cost per hour is 240,000/1,600 = $150. Planned is 250,000/2,000 = $125. Higher cost per unit of output means lower efficiency. Total spend was lower, but that does not show economy or efficiency per hour.
Did you get it right without looking?
One question tells you little. A timed set on Cost reductions and value enhancement shows your real accuracy, how long you take and where you lose marks.
More Cost reductions and value enhancement questions
- A council library service spent $200,000 on staffing in the year, which was $20,000 less than budget for the same quality of staff. It lent …
- A company is value engineering a product with a target selling price of $80 and a required profit margin of 25% of selling price. The curren…
- A manufacturer redesigns a product before it goes into production, aiming to cut cost while keeping the functions the customer values. Which…
- A company's target cost for a product is $45 per unit. The current estimated cost is $52 per unit. What is the cost gap, and what action doe…
- Zeta Ltd plans to launch a new product. Market research shows customers will pay $80 per unit. The company requires a profit margin of 25% o…
- A company uses target costing for a new product. The market research suggests a selling price of $80 per unit, and the company requires a pr…