A department had 500 budgeted hours, of which 450 were actually worked and 400 of those were active. Output achieved had a standard time of 360 hours. Budgeted capacity was 500 hours, and the hours actually available were 450 due to absenteeism. What is the capacity ratio (actual hours worked / budgeted hours)?

The capacity ratio is 90.0%, found by dividing actual hours worked, 450, by budgeted hours, 500. It shows how much of the planned time was actually used. The 72.0% figure is the production volume ratio.

  1. A72.0%
  2. B80.0%
  3. C90.0%Correct
  4. D112.5%

Explanation

Capacity ratio = actual hours worked / budgeted hours = 450/500 = 90.0%. Using the standard hours of 360 would give 72.0%, which is the production volume ratio, not the capacity ratio.

Did you get it right without looking?

One question tells you little. A timed set on Accounting for material, labour and overheads shows your real accuracy, how long you take and where you lose marks.

More Accounting for material, labour and overheads questions