Budgeted fixed overheads were $360,000 for 30,000 units. Actual output was 32,000 units and actual fixed overheads were $372,000. Overheads are absorbed per unit. Of the total over- or under-absorption, how much is due to the volume of output differing from budget?

The volume effect is the extra 2,000 units produced multiplied by the $12 per unit rate, giving $24,000 over-absorbed. This is partly offset by $12,000 of higher spending, so the net over-absorption is $12,000, but the volume element alone is $24,000.

  1. A$24,000 over-absorbedCorrect
  2. B$12,000 under-absorbed
  3. C$12,000 over-absorbed
  4. D$24,000 under-absorbed

Explanation

Rate = $360,000 / 30,000 = $12 per unit. Absorbed = 32,000 x $12 = $384,000. Total over-absorption = $384,000 - $372,000 = $12,000. Expenditure difference: $372,000 - $360,000 = $12,000 adverse (under-absorbed effect). Volume effect = 2,000 x $12 = $24,000 over-absorbed. Net = $24,000 - $12,000 = $12,000 over.

Did you get it right without looking?

One question tells you little. A timed set on Accounting for material, labour and overheads shows your real accuracy, how long you take and where you lose marks.

More Accounting for material, labour and overheads questions