A department's budget was 2,000 labour hours costing $24,000, with 40% of the cost fixed. Actual hours were 2,500 and actual cost was $28,100. What is the variance against the flexed budget?

The flexed budget is $27,600, so actual cost of $28,100 is $500 adverse; this item has no matching option.

  1. A$900 favourable
  2. B$4,100 adverse
  3. C$900 adverseCorrect
  4. D$1,700 favourable

Explanation

Fixed = 9,600; variable = 14,400, i.e. $7.20 per hour. Flexed = 2,500 x 7.20 = 18,000 + 9,600 = $27,600. Actual 28,100 minus 27,600 = $500 adverse. Correction needed.